Reference profile · Iraq · C&I rooftop

Self-consume the kWh. Schedule around the outage.

A 2.4 MWp rooftop PV system with 500 kWh of LFP storage carries an Iraqi manufacturing complex through the daytime production shift on solar — and bridges the evening shift across the predictable grid-loss window without firing the on-site diesel set.

Location  Baghdad, Iraq Topology  Grid-tied C&I + BESS bridging Capacity  2.4 MWp PV · 500 kWh LFP Reference profile  v1 · 2026
0MWp
Rooftop PV
Ballasted, 10° tilt, 22,400 m² roof
0kWh
LFP storage
~4 hr evening-shift bridging
0GWh / yr
Year-1 PV yield
~1,700 kWh/kWp · NASA POWER
0%
Self-consumption
PV kWh consumed on site
0%
Diesel runtime cut
~310,000 L/yr fuel saved
The challenge

Baghdad's grid is reliable on Wednesday. Not on Thursday.

The site is a 22,400 m² manufacturing complex with a 1.6 MW continuous daytime load across two production lines, a 900 kW evening shift on a single line, and a permanent 120 kW office and warehouse base. Pre-project, the entire site was carried by the national grid when available and by a 2.0 MVA diesel station during scheduled outages — which in Baghdad's Karkh sector run between 2 and 6 hours of every working day.

The commercial problem isn't the diesel itself — it's diesel runtime as a function of an unpredictable grid. Fuel deliveries are quoted weekly, tariff-loaded, and a single late tanker can stop the line for half a shift. Diesel runtime had grown to ~3,800 hours/year across the two sets, with an avoided fuel-cost line item that was the second-largest controllable OpEx after raw materials.

The brief: shave PV against the daytime load with as close to 100% self-consumption as possible, cover the evening-shift load through the typical 2–3 hour evening outage window with LFP, and only run the diesel when both PV and BESS are unavailable — turning the diesel from a primary fuel source into a true backup-of-last-resort.

Site & load baseline

  • Daytime load: 1.6 MW continuous (two lines)
  • Evening shift: 900 kW (one line, 16:00–24:00)
  • Base load: 120 kW 24/7
  • Pre-project diesel: ~3,800 hr/yr · ~395,000 L/yr
  • Typical outage: 2–6 hr/working-day
  • Latitude: 33° N · Baghdad, Karkh sector
  • GHI: ~2,030 kWh/m²/yr (NASA POWER)
  • Roof: 22,400 m² shed roofs, 7° structural tilt
The approach

Size against the load curve, not against the roof area.

The 22,400 m² roof would hold ~4.0 MWp at typical commercial spacing — but at that size, midday solar would routinely exceed daytime load, exporting kWh into a grid that doesn't currently buy them back at a meaningful tariff. The system is sized at 2.4 MWp specifically against the 1.6 MW daytime load curve plus the BESS charge window, holding self-consumption above 92% across the year and leaving roof area in reserve for a later 1.6 MWp expansion if and when net-export tariffs improve.

Three engineering decisions diverge from a typical 2.4 MWp C&I rooftop:

  1. 1Hybrid inverter, not separate PV+BESS strings. A single hybrid string-inverter family handles both the PV MPPT and BESS PCS function. The MV switchboard sees one feeder, not two, and the EMS arbitrates priority — PV-first to load, then PV-to-BESS, then grid charge during off-peak. Saves ~14% on switchgear capex and simplifies the future expansion path.
  2. 2BESS sized to the evening outage window, not to a sustainability target. 500 kWh at the 900 kW evening-shift load is ~33 minutes of full bridging, or ~4 hours at the 120 kW base load and partial line. The evening outage in this Baghdad sector typically lasts 2–3 hours and aligns with one production line draw-down; the BESS exists to keep that specific transition smooth.
  3. 3Roof-load engineering before module choice. The shed roofs were originally designed for production loads, not for PV ballast. A pre-installation structural survey re-rated 6 of 14 bays for additional dead load, two required local steel reinforcement, and one bay was excluded entirely from the PV layout. The structural pass took 4 weeks and reduced the final installable area by ~8% — both numbers cheaper than a roof failure under wet ballast and snow load.
System architecture

Single-line view: PV / BESS / grid / diesel → load.

A simple four-source architecture coupled at the building's main 11 kV switchboard, with the hybrid inverter family providing both PV conversion and BESS PCS function. The diesel set is electrically isolated from the BESS and re-enters the bus only on a full grid-loss event with BESS energy below threshold.

Rooftop PV2.4 MWp LFP BESS500 kWh Utility grid11 kV · intermittent G2.0 MVAbackup Hybrid inverter / EMS · 11 kV main switchboard Daytime production 1.6 MW · two lines PV-first dispatch Evening shift 900 kW · one line BESS bridging Base load 120 kW · 24/7 Office + warehouse EMS controller PV-first · BESS grid-last priority
PV generation
LFP storage
Utility grid
Diesel / loads
Controls
Bill of materials

Indicative equipment stack.

Component selection is illustrative — final BoM in any binding TPC delivery is calibrated to roof structural survey, available utility tariff structure, and the supplier list current at quote time. Primary equipment ships factory-direct to a CIF Baghdad incoterm; structural reinforcement and HV scope are procured locally under TPC engineering supervision.

ComponentSpecificationQtySource
PV moduleN-Type TOPCon mono · 575 W · 144-cell · IEC 61215 / 617304,175Factory-direct
Ballasted mountingAluminium 6005-T5, 10° tilt, structural-survey engineered ballast~2.4 MWpFactory-direct
Roof reinforcementSteel C-section secondary, 8 reinforced bays per structural pass1 lotSite-procured
Hybrid string inverter1500 V DC · 200 kW · integrated PV MPPT + BESS PCS · IP6612Factory-direct
LFP battery cabinetIndoor 500 kWh · liquid-cooled · UL 9540A · IEC 626191Factory-direct
Energy management systemEMS · PV-first / BESS / grid-last dispatch · production line interlock · web dashboard1Factory-direct
11 kV switchboardExisting main switchboard retrofit · PV+BESS feeder · ATS coordination with diesel1 retrofitSite-procured
DC combiner / SPDs1500 V Type II surge arresters, fused string combiners36Factory-direct
Cabling & earthing1500 V DC PV cable, LV armoured, IEC 60502~3.6 kmSite-procured
Fire detectionAspirating smoke detection in BESS room · NFPA 855 setback compliance1 lotSite-procured
Commissioning & tariff modellingFAT + SAT + 30-day load profile validation + self-consumption optimisation report1 packageTPC engineering
Year-1 PV generation

Modelled monthly yield, calibrated to NASA POWER Baghdad data.

Monthly generation is computed from public NASA POWER irradiance for 33°N Baghdad applied to the as-designed 2.4 MWp rooftop at PR 0.78 — typical for low-tilt ballasted rooftop installations with moderate dust loading. Hover any bar for the underlying figure.

Monthly PV generation — Year 1 (modelled)

Annual total: 4.1 GWh · ~1,700 kWh/kWp · PR 0.78
Jan · 256 MWh
Feb · 262 MWh
Mar · 331 MWh
Apr · 354 MWh
May · 406 MWh
Jun · 438 MWh
Jul · 441 MWh
Aug · 418 MWh
Sep · 365 MWh
Oct · 319 MWh
Nov · 264 MWh
Dec · 232 MWh
JanFebMarAprMayJunJulAugSepOctNovDec

The annual profile is dominated by the May–August plateau (~400–440 MWh/month) where PV alone covers the full daytime production-line load. Self-consumption tops 95% in those months and the BESS reaches full charge by 14:00 ready for the evening outage window. Winter months see self-consumption above 88% even at the production-line draw-down — the system was sized for that case, not for the summer peak.

Lessons learned

Three engineering insights worth carrying forward.

01 / SIZING

Size against the load curve, not against the roof.

Filling every available square metre of roof produces a system that exports kWh into a grid that doesn't pay for them, while leaving the BESS occasionally undercharged at evening peak. The 2.4 MWp size was reached after running 12 months of half-hour interval load data through the dispatch model — every 200 kWp added beyond that point pushed self-consumption down by 3–4 percentage points with no commercial offset.

02 / STRUCTURE

Audit the roof before you order the panels.

The 4-week structural pass that excluded one bay and reinforced two more cost a single-digit percentage of the project but prevented a real failure mode: ballast load + summer thermal expansion + a single sand-storm wind event in an under-rated bay. The same pass also identified two roof penetrations that would have been hit by the original cable routing.

03 / EMS

The EMS is the asset. The hardware is the cost line.

The 92% self-consumption figure is an EMS outcome, not a hardware outcome — it is the dispatch logic deciding, every 5 seconds, whether the next PV kWh charges the BESS, displaces grid, or services a load directly. Specifying the EMS first and the inverter family second produced a better commercial result than the reverse pathway any contractor would default to.

The factory measures success in pieces shipped per shift, not kilowatt-hours generated. After the system went in, the evening shift stopped lining up at the diesel set's start-up time waiting for the bus to come back. That was the operational change worth more than the fuel saving on the spreadsheet.
C&I delivery lead · MENA rooftop engagements · TPC engineering

Quote is illustrative of the engineering posture TPC brings to C&I rooftop engagements in intermittent-grid markets. This reference profile is not tied to a named or contracted client; site-specific testimonials are released only with the operator's signed consent under the engagement NDA.

Reference profile. This page describes a typical engagement scope, equipment stack and modelled outcome representative of TPC's C&I rooftop delivery in intermittent-grid markets — not a specific contracted client project. Generation figures are computed from public NASA POWER solar irradiance data for the Baghdad / 33°N zone applied to the equipment specification described above. Final pricing, system size, self-consumption, and delivered yield in any binding TPC engagement depend on roof structural survey, load profile, available tariff, and the supplier list current at quote time.

Working on a similar engagement?

C&I rooftop in an intermittent-grid market, evening-shift bridging, or self-consumption optimisation under emerging-tariff structures — TPC's engineering team will scope the same equipment envelope for your project under a one-business-day SLA.